| December 18, 2001 The amount of activity at the east campus is amazing. The DeVos Communication Center has been insulated, waterproofed, framed for interior walls and windows, and stairs take form. | ||||
| The Bridge | DeVos Communication Center | Prince Conference Center | ||||
![]() New landscaping along the road bed. |
![]() The roof gets a finishing touch before windows go in. |
![]() Waterproofing the exterior cinderblock walls. |
![]() The north side and its bright yellow insulation. |
|
![]() The east campus is a land of mud, trucks, and constant change. |
![]() Coit Ave Gravel Inc. delivers cement ingredients. |
![]() Old fashion teamwork gets the window frames installed. |
![]() Two workers build a staircase deep inside the DeVos building. |
|
![]() The ground floor and the pipe fitter's yard. |
![]() The CAS broadcast studio. |
![]() CAS's new broadcast studio takes shape. |
![]() A view into the CAS studio from the main floor. |
|
![]() The main lobby upon exiting the bridge. |
![]() The lobby's awesome southwest view will make it THE place to be on sunny days between classes. |
![]() The second floor is divided into offices and classrooms. |
![]() The classrooms will have a magnificent view north. |
|
![]() Electricians install outlets and run conduit. |
![]() Air conditioning units occupy the third floor in mass. |
![]() Buggs Bunny takes a break from welding. |