We have completed our final design for both the onion farm and for Buttermilk Creek.

Onion Farm:

Team 13 has chosen Design Alternative 2.

Design Includes:

  • Detention pond designed for 100-year storm
  • Emergency spillway
  • Overflow structure, inlet located at elevation of a 25-year storm
  • Concrete pipe connection into storm sewer at 36th Avenue
  • 2 Manholes

 

Buttermilk Creek:

Team 13 has chosen Design Alternative 2.

Design Includes:

  • 200' x 150' detention pond designed for 100-year storm
  • Emergency Spillway
  • Inflow Lateral Spillway
  • Orifice Pipe for outflow

 

See our Downloads page for a complete construction plan set.

 

 

 
 